Project Timeline & Delivery Programme: 50% Faster Than Traditional
Manufacturing offsite while destination site permits, excavation and foundations are executed simultaneously: how concurrent engineering compresses 12-month builds into 12 to 16 weeks.
Engineering & Operational Principles
Concurrent Engineering: Parallel Workstreams
Traditional building is sequential (foundation -> structure -> walls -> fit-out). Offsite modular builds foundations on site while bathrooms, kitchens, joinery and MEP are completed concurrently in the factory.
4-Phase Schedule Breakdown
Weeks 1-4: Architectural BIM freeze & engineering approvals. Weeks 5-10: Automated offsite production & local foundation pouring. Weeks 11-12: Multimodal transport. Weeks 13-14: Crane erection and commissioning.