D06 · TECHNICAL LOGISTICS PROTOCOL Eurocode & Incoterms 2020 Compliant

Project Timeline & Delivery Programme: 50% Faster Than Traditional

Manufacturing offsite while destination site permits, excavation and foundations are executed simultaneously: how concurrent engineering compresses 12-month builds into 12 to 16 weeks.

Production Origin
İstanbul / Türkiye
Industrial Modular Plant
Typical Delivery
8 - 12 Weeks
From Design Sign-Off
Structural Standard
EN 1090-2 & EN 1993
Eurocode Steel Execution
Logistics & Export Desk
SERMODULA Global
Technical Delivery Coordination

Engineering & Operational Principles

Concurrent Engineering: Parallel Workstreams

Traditional building is sequential (foundation -> structure -> walls -> fit-out). Offsite modular builds foundations on site while bathrooms, kitchens, joinery and MEP are completed concurrently in the factory.

Verified Protocol Scope

4-Phase Schedule Breakdown

Weeks 1-4: Architectural BIM freeze & engineering approvals. Weeks 5-10: Automated offsite production & local foundation pouring. Weeks 11-12: Multimodal transport. Weeks 13-14: Crane erection and commissioning.

Verified Protocol Scope
Knowledge Base

Frequently Asked Questions

How long does a standard single-family home take from order to move-in?
Typically 12 to 16 weeks, assuming municipal building permits and zoning permissions are already secured at the destination municipality.
Can multi-family apartment buildings be delivered in phases?
Yes. For developments of 20 to 100+ dwellings, modules are scheduled in batches of 10 to 15 units weekly, preventing jobsite overcrowding.
Does weather impact offsite fabrication speed?
No. Offsite manufacturing takes place inside climate-controlled facilities. Steel welding, drywalling and paint cure under constant temperature and humidity.
How much time is saved compared to reinforced concrete construction?
Typically 50% to 70% time reduction. A multi-family project requiring 18 months in traditional concrete is completed in 5 to 7 months with SERMODULA.
What is the critical path item in a modular project programme?
The local building permit approval and the architectural BIM model freeze. Once drawings are frozen, procurement and fabrication commence without delay.