ISO 9001 / FAT ITP-05 Inspection & Test Plan / 3D Laser Metrology

Off-Site Quality Control, ITP & Tolerances

Multi-gate Inspection and Test Plan (ITP), 3D laser geometric metrology ensuring ±1.5 mm diagonal accuracy, and comprehensive Factory Acceptance Testing (FAT) documentation.

Technical Subsystem Keywords: # off-site quality control ITP # millimeter laser tolerance check # factory acceptance testing FAT # traceability log sheet

Key Engineering & Performance Metrics

Diagonal Tolerance ±1.5 mm across 12-meter chassis length
Itp Gates 7-Stage gate hold points with photo sign-offs
Weld Testing 100% Visual (VT) + sample Ultrasonic (UT)
Documentation Digital As-Built & Quality Dossier with QR tag
Structural Mechanics

System Architecture & Structural Mechanics

Quality in volumetric construction depends on zero deviations before modules leave the factory floor. Every SERMODULA unit passes an Inspection and Test Plan (ITP) comprising 7 mandatory gates: raw material mill verification, welded chassis metrology, corrosion treatment, envelope insulation sealing, MEP pressure integrity, interior dry-lining finish, and final export wrapping.
Norm Compliance

Technical Standards & Compliance Matrix

Verified design standards, testing criteria and tolerance controls.

Technical Parameter #1

Structural & Seismic

Applicable Standard
Eurocode 3 (EN 1993) & Eurocode 8 (EN 1998)
Limit / Rating
S355JR / S275JR, DCM/DCH Ductility
Verification Method
3D FEM Analysis & Verification Report
Technical Parameter #2

Steel Fabrication & Welding

Applicable Standard
EN 1090-2 (EXC3) / ISO 3834-2
Limit / Rating
EXC3 Execution Class, CE Marked
Verification Method
NDT Ultrasonic & Magnetic Testing
Technical Parameter #3

Corrosion Protection

Applicable Standard
ISO 12944 (C3 / C4 Dayanım)
Limit / Rating
Epoxy Primer + PU Topcoat (160–240 µm)
Verification Method
DFT Gauge & Cross-Cut Adhesion
Technical Parameter #4

Fire & Acoustic Separation

Applicable Standard
EN 13501-2 / ISO 717-1
Limit / Rating
REI 60–120 · Rw ≥ 56 dB / Ln,w ≤ 48 dB
Verification Method
Accredited Lab Test Certification
Technical Parameter #5

Dimensional Tolerances

Applicable Standard
EN 1090-2 D Sınıfı & ISO 2768
Limit / Rating
Diagonal & Vertical max. ±2.0 mm
Verification Method
3D Laser Metrology & Calibration Jig
Factory Production

Factory Pre-fabrication & Quality Verification (ITP)

Upon passing final gate inspection, a unique digital QR passport is affixed to the structural plate, granting the client and on-site team instant access to inspection logs, electrical test certificates, and lifting instructions.
Interface Discipline

Layer Architecture & On-site Interface

01

Structural Node & Joint

Cast-steel corner blocks and EN 14399 grade 10.9 high-strength structural bolts guarantee instant load transfer.

02

Acoustic & Fire Seals

Continuous EPDM weather seals, intumescent fire gaskets and elastomeric vibration isolators installed between volumetric cells.

03

Vertical Shaft Coupling

Vertical MEP risers align on precision axes with flexible compensator couplings for rapid single-point hookup.

04

Certified Crane Rigging

Integrated rigging pick-points calibrated to volumetric center of gravity ensure balanced, tilt-free crane erection.

Technology Ecosystem

Explore Other Engineering Subsystems

Coordinated building envelope, MEP, acoustic, connection and quality control engineering systems.

Direct Architectural & Engineering Leadership

Structure Your Technical Specification & Engineering Baseline

Share your structural parameters, Eurocode design requirements and target typology for a verified engineering feasibility review with the SERMODULA Engineering & Technical Team.

SERMODULA Structural Engineering Desk Eurocode 3 & 8 / EN 1090-2 Technical Coordination
Direct (GSM): +90 (505) 507 04 18
Central Switchboard: +90 (216) 614 04 34
Engineering Email: [email protected]
Knowledge Base

Frequently Asked Questions

Can clients inspect their modules during production?
Yes. Clients or their independent third-party inspectors (e.g. TÜV, SGS) are welcome to attend milestone hold-point inspections at our Istanbul facilities.
What happens if a module fails dimensional inspection?
Any unit exceeding ±1.5 mm tolerance is placed on hold and re-calibrated on laser alignment jigs before progressing to insulation and MEP fit-out.
Is full documentation provided upon delivery?
Yes. A comprehensive As-Built dossier including steel certificates, pressure tests, and electrical compliance is delivered digitally and physically.
How are modules protected during sea or road freight?
Units are wrapped in heavy-duty UV-stabilized shrink wrap with desiccant packs inside to prevent condensation and road spray damage.
What warranty is offered on the structural frame?
SERMODULA offers a 10-year structural warranty on all steel load-bearing frames, alongside standard component warranties.